Energy transition at Feldhaus Klinker - Update

Another step closer to CO2-free brick production

Thanks to the frost-free weather, the assembly work for the solar modules could proceed. Currently, over 36,000 m² of solar modules have been installed - the equivalent of four and a half soccer fields. And the work is not yet finished: Further hall roofs are being prepared for assembly. In parallel, work is underway on the ring line that will bring the energy to the inverters and the new transformer stations. Here, the work is 90% complete. The construction measures are thus on schedule.